What should you check before approving a BOQ?
A low total does not necessarily describe the same building. Compare estimates against the same drawings, material specifications and measurement rules.
- Drawing version: identify the plans used to measure the work. Updated layouts can change quantities.
- Item descriptions: check material specifications, units and what labour or equipment is included.
- Exclusions: ask whether site preparation, external works, services and other project requirements are included or separately priced.
- Rate basis: distinguish assumptions from confirmed supplier or contractor quotations. Confirm validity and applicable commercial terms.
- Changes: agree how revised quantities and owner selections will be recorded and priced.
Keep the approved BOQ and drawing revision together. Compare subsequent changes against that baseline rather than overwriting the original estimate.